18/12/2011 Received Electricity Connection.
15/11/2011 Completed and ready to handover. Received Occupancy Certificate.
15/05/2011 Completed Flooring, Doors & Windows Fixing, Electrical Fixing and ready to handover for Interior work.
28/01/2011 Toilet Tile work completed. Floor Tile work started. Painting Work started.
15/12/2010 External Plastering Completing..
26/08/2010 Internal Plastering Completing..
Panoramic View from Top Floor updated.
03/07/2010 Fourth Roof (Last) Slab Casting completed.
8/6/10 Fourth Floor Slab Casting in Progress. Brick work started in second floor. (see photos)
21/5/10 Third Floor slab casting progressing and will be completed by 26 May 10. Brick work started from 1st Floor (see photos on the left).
Project Started. Currently Piling works are being done